Coming Soon: Route 638 (South River Road) Bridge Replacement
Cost and schedule ►
Public outreach ►
The proposed project will replace the existing bridge on South River Road in Caroline County over the South River with a new bridge. The new bridge will be longer than the existing bridge, with road shoulders.
The existing bridge is 81 feet long and 28 feet wide. The proposed replacement bridge would be build on the existing bridge's alignment, but would be 110 feet long and 28 feet wide. The travel lanes on the replacement bridge will 9 feet wide, with 5-foot shoulders.
During construction, South River Road would be closed to through traffic at the bridge over South River. A posted detour would be in place for an estimated year (12 months).
Notice of Willingness
A Notice of Willingness is posted on this project from August 23-September 7, 2022.
Project Environmental Document
Newspaper Advertisement
If your concerns cannot be satisfied, VDOT is willing to hold a public hearing. You may request that a public hearing be held by sending a written request to Ms. Jessica Graves, Project Manager, VDOT, 87 Deacon Road, Fredericksburg, VA 22405 on or prior to September 7, 2022. If a request for a public hearing is received, notice of date, time and place of the hearing will be posted.
VDOT ensures nondiscrimination and equal employment in all programs and activities in accordance with Title VI and Title VII of the Civil Rights Act of 1964. If you need special assistance for persons with disabilities or limited English proficiency, contact the project manager listed above at 540-899-4288 or TTY/TDD 711.
Benefits
- Improves bridge condition through total replacement of structure
- Installs a longer bridge, with shoulders
- Installs new guardrail
- By improving the bridge's condition, allows South River Road to remain open to vehicles of all weights
Major Milestones
Public Involvement: A Notice of Willingness was posted from August 23-September 7, 2022
Advertisement for Construction: This project would be advertised to potential bidders for construction in September 2024.
Construction and Detour: Early 2025-March 2026
Project complete: March 2026
Resources
Jessica Graves, VDOT Project Manager
540-899-4267
Alexis Breeden, VDOT Communications
(540) 547-1752
Major funding source: State of Good Repair
Phase: Proposed
UPC: 113852
State ID: 0638-016-640
Federal ID: STP-016-6(060)
Lat/Long: 38.110302859348245, -77.43025235129161
Locality:
Caroline