STAUNTON – The following is a list of highway work that may affect traffic in the Staunton transportation district during the coming weeks. The Staunton District consists of 11 counties from the Alleghany Highlands to the northern Shenandoah Valley: Alleghany, Bath, Rockbridge, Highland, Augusta, Rockingham, Page, Shenandoah, Frederick, Clarke and Warren.
Scheduled work is subject to change due to inclement weather and material supplies. Motorists are advised to watch for slow-moving tractors during mowing operations. When traveling through a work zone, be alert to periodic changes in traffic patterns and lane closures.
*NEW* or *UPDATE* indicates a new or revised entry since last week’s report.
ALLEGHANY COUNTY
INTERSTATE 64
Mile marker 9 to 25, eastbound and westbound – Alternating lane closures for maintenance of various bridges, Monday to Friday from 7 a.m. to 7 p.m. through November 13.
*NEW* Mile marker 21 to 19, westbound – Left lane closed for repairs to cable barrier, Wednesday from 8:30 a.m. to 4:30 p.m.
*UPDATE* Mile marker 34 to 31, westbound – Shoulder closures for tree removal operations, Monday to Friday from 7:30 a.m. to 5:30 p.m.
PRIMARY ROADS
*NEW* Route 18 (Potts Creek Road) – Shoulder closures between Route 1215 (Cherokee Trail) and Route 656 (Redbud Road) for tree removal operations, Monday to Friday from 7 a.m. to 5 p.m.
*NEW* Route 42 (Forty-Two Road) – Shoulder closures between Route 636 (Morgan Drive) and Route 630 (Griffith Road) for tree removal operations, Monday to Friday from 7 a.m. to 5 p.m.
*NEW* Route 60 (Midland Trail) – Shoulder closures near intersection with Route 600 (Rumsey Road) for tree removal operations, Monday to Friday from 7 a.m. to 5 p.m.
*NEW* Route 311 (Kanawha Trail) – Shoulder closures between Route 602 (Big Ridge Road) and Route 679 (Sweet Springs Lane) for tree removal operations, Monday to Friday from 7 a.m. to 5 p.m.
Various roads – Flagger traffic control for tree and debris removal, drainage work, shoulder repairs and brush cutting. Weekdays from 8:30 a.m. to 4 p.m.
SECONDARY ROADS
Route 696 (Selma Low Moor Road) – Temporary signals control traffic 24/7 between I-64 and Route 616 (Rich Patch Road) during bridge replacement at Karnes Creek. Estimated project completion in fall 2021.
*UPDATE* Various roads – Flagger traffic control for pipe replacements, ditch work, tree removal, shoulder repairs and brush cutting. Weekdays from 8:30 a.m. to 4 p.m.
BATH COUNTY
PRIMARY ROADS
Various roads – Flagger traffic control for brush cutting. Weekdays from 8:30 a.m. to 4 p.m.
SECONDARY ROADS
Various roads – Flagger traffic control for brush cutting. Weekdays from 8:30 a.m. to 4 p.m.
ROCKBRIDGE COUNTY
INTERSTATE 64
Exit 55, eastbound and westbound – Right shoulder closures along off-ramps for sign maintenance, Monday to Friday from 8 a.m. to 5 p.m. through November 13.
INTERSTATE 81
Mile marker 177 to 183 including Exit 180 off-ramps, northbound and southbound – Shoulder closures for sign maintenance, Monday to Friday from 8 a.m. to 5 p.m. through November 13.
*NEW* Mile marker 192 to 193, northbound – Shoulder closures for sign work, Wednesday and Thursday from 7 a.m. to 5 p.m.
*UPDATE* Mile marker 197 to 196, southbound – Shoulder closures for sign work, Monday and Tuesday from 7 a.m. to 5 p.m.
PRIMARY ROADS
*NEW* Route 11 (Lee Highway) – Northbound and southbound right lane closures between Route 11 Business (Main Street, Lexington) and Route 631 (Old Buena Vista Road) for inspection of Maury River bridge, Tuesday from 8:30 a.m. to 4:30 p.m.
*NEW* Route 60 (West 29th Street, Buena Vista) – Alternating lane closures between Beech Avenue and western city limits for milling and paving, November 12-20 from 7 a.m. to 5 p.m.
Route 252 (Brownsville Turnpike) – Shoulder closures for tree removal operations between Route 710 (Swope Lane) and Route 724 (Sterrett Road), Monday to Friday from 7 a.m. to 6 p.m.
*NEW* Route 501 (Magnolia Avenue, Buena Vista) – Flagger and pilot-truck traffic control between Third Street and southern city limits for milling and paving, Tuesday to Friday from 7 a.m. to 5 p.m.
Various roads – Mobile traffic control for mowing. Flagger traffic control for pipe replacement, ditch work, tree removal, shoulder repairs, pavement patching and brush cutting. Weekdays from 8:30 a.m. to 4 p.m.
SECONDARY ROADS
Various roads – Mobile traffic control for mowing. Flagger traffic control for grading, pipe replacement, ditch work, tree removal, pavement patching, shoulder repairs and brush cutting. Weekdays from 8:30 a.m. to 4 p.m.
HIGHLAND COUNTY
PRIMARY ROADS
*UPDATE* Route 220 (Potomac River Road) – Alternating lane closures for paving operations between Route 632 (The Pines Road) and West Virginia line, 6 a.m. to 9 p.m. through November 20.
Various roads – Flagger traffic control for tree removal, pavement patching and shoulder repairs. Weekdays from 8:30 a.m. to 4 p.m.
SECONDARY ROADS
Various roads – Mobile traffic control for mowing. Flagger traffic control for pipe cleaning, tree removal, pavement patching, ditch work and adding stone to unpaved roads. Weekdays from 8:30 a.m. to 4 p.m.
AUGUSTA COUNTY
INTERSTATE 64
No lane closures reported.
INTERSTATE 81
*NEW* Mile marker 221 to 219, southbound – Overnight left lane closure for guardrail repair, 9 p.m. Thursday to 1 a.m. Friday.
PRIMARY ROADS
*NEW* Route 11 (Lee Highway) – Overnight mobile lane closures for paving operations between Staunton city limits and Route 612 (Laurel Hill Road), Monday through Thursday nights from 7 p.m. to 7 a.m.
Route 11 (Lee-Jackson Highway) – Southbound shoulder closures between Route 1402 (First Street) and Route 1409 (Mitchell Lane) for utility work, Monday to Thursday from 8 a.m. to 5 p.m. through November 19.
Route 250 (Churchville Avenue) – Traffic diversion in place for Bell Creek bridge replacement between Route 732 (Franks Mill Road) and western intersection with Route 840 (Old Churchville Road). Detour uses temporary bridge and portion of Route 732. Work zone speed limit 35 miles an hour. Estimated project completion summer 2021.
*NEW* Route 262 (Woodrow Wilson Parkway) – Shoulder closures for inspection of bridge over Route 703 (Buttermilk Spring Road), Monday from 8:30 a.m. to 4:30 p.m.
SECONDARY ROADS
Route 608 (Cold Springs Road) – Flagger traffic control between Route 610 (Howardsville Turnpike) and Route 1511 (Flory Avenue) for maintenance to South River bridge, Monday to Friday from 7 a.m. to 5 p.m. through November 13.
Route 616 (Humbert Road) – Shoulder closures between Route 865 (Rockfish Road) and Route 608 (Battlefield Road) for utility work, 9 a.m. to 3 p.m. through December 31.
*NEW* Route 634 (Patton Farm Road) – Shoulder closures between Route 610 (Howardsville Turnpike) and Route 639 (Wayne Avenue) for utility work, 9 a.m. to 3 p.m. through December 31.
Route 732 (Franks Mill Road) – Traffic pattern change for Bell Creek bridge replacement near intersection with Route 250 (Churchville Avenue). Part of Route 732 serves as detour for Route 250 traffic. Work zone speed limit 35 miles an hour. Estimated project completion summer 2021.
Various roads – Mobile work zones in the Swoope, Craigsville, Verona, Moscow, Fishersville and Mint Spring areas for mowing, pothole patching, brush cutting and grading non-hard surface roads. Weekdays from 8 a.m. to 4 p.m. through November 30.
ROCKINGHAM COUNTY
INTERSTATE 81
*NEW* Mile marker 242 to 244, northbound – Overnight right lane closure for pavement patching, 8 p.m. Monday to 7 a.m. Tuesday.
*NEW* Mile marker 242 to 248, northbound and southbound – Overnight left lane closures for survey and utility work, Monday through Wednesday nights from 9 p.m. to 6 a.m.
*NEW* Mile marker 244 to 245, northbound – Overnight alternating lane closures for maintenance to Blacks Run bridge, Monday through Thursday nights from 8 p.m. to 7 a.m.
*NEW* Mile marker 246 to 249 including exit 247 off-ramps, northbound and southbound – Shoulder closures for sign work, Monday to Friday from 8 a.m. to 5 p.m. through November 20.
*UPDATE* Mile marker 257 to 259, northbound and southbound – Overnight left lane closures for removal of old Route 11 bridge piers, Monday through Thursday nights from 8 p.m. to 7 a.m. Northbound and southbound shoulders closed 24/7. Traffic restrictions are for bridge replacement and interchange improvements with estimated completion in spring 2021.
PRIMARY ROADS
Route 11 (Valley Pike) – Alternating lane closures as needed for pavement marking in the area of the I-81 exit 257 interchange at Mauzy, Monday to Friday from 9 a.m. to 3 p.m. Work is part of bridge replacement and interchange improvements with estimated project completion in spring 2021.
Route 33 (Rawley Pike) – Flagger traffic control for paving operations between Dry Run Road and Laurel Wood Lane, Monday to Friday 8 a.m. to 4:30 p.m. through November 20.
Route 253 (Port Republic Road) – Traffic controlled by flaggers and pilot trucks between Route 672 (Pineville Road) and Route 340 (Eastside Highway) for paving and shoulder improvements, Monday to Friday from 7 a.m. to 7 p.m. through November 20.
Route 259 (Mayland Road) – Alternating lane closures as needed for pavement marking in the area of the I-81 exit 257 interchange at Mauzy, Monday to Friday from 9 a.m. to 3 p.m. Work is part of bridge replacement and interchange improvements with estimated project completion in spring 2021.
SECONDARY ROADS
Route 991 (Jacob Burner Drive) – Road closed through November 12 between Route 996 (McGaheysville Road) and Route 642 (Cave Hill Road) for bridge rehabilitation at Stoney Run. Follow posted detour.
PAGE COUNTY
PRIMARY ROADS
Route 211 – Single-lane traffic between Route 615 (Egypt Bend Road) and Route 646 (Oak Leaf Road). Westbound traffic uses median crossover to share eastbound bridge over Shenandoah River South Fork. Work zone speed limit 45 miles an hour. Traffic restrictions are for westbound bridge replacement with estimated completion in summer 2022.
SECONDARY ROADS
No lane closures reported.
SHENANDOAH COUNTY
INTERSTATE 81
Mile marker 268 to 273, northbound and southbound – Overnight alternating lane closures for bridge maintenance at various locations, Monday to Thursday nights from 8 p.m. to 7 a.m. through November 13.
*UPDATE* Mile marker 295 to 296, northbound – Shoulder closures for sign installation, Monday to Thursday from 7 a.m. to 5 a.m.
PRIMARY ROADS
Route 11 (Old Valley Pike) – Alternating lane closures for paving operations in divided-highway section between town of Strasburg and Route 641 (Locust Grove Road). 6:30 a.m. to 7 p.m. through November 13.
Route 55/48 (John Marshall Highway) – Alternating lane closures for utility work between Route 633 (Red Bud Road) and Frederick County line, 9 a.m. to 3:30 p.m. through January 10.
SECONDARY ROADS
Route 620 (Smith Creek Road) – Road closed just south of intersection with Route 732 (Cardinal Road) for Smith Creek bridge replacement. Follow posted detour. Estimated project completion December 2020.
Route 623 (Coal Mine Road) – Road closed just east of Route 606 (Moores Ford Road) for Cedar Creek bridge replacement at Frederick County line. Follow posted detour. Estimated project completion June 2021.
Route 698 (Orchard Drive, Mount Jackson) – Road closed just west of Route 263 (Bryce Boulevard/Orkney Grade) for Mill Creek bridge replacement. Follow posted detour. Estimated project completion June 2021.
Various roads – Flagger traffic control for utility tree trimming, Monday to Friday during daylight hours.
FREDERICK COUNTY
INTERSTATE 81
*NEW* Mile marker 301 to 304 including exit 302 off-ramps, northbound and southbound – Shoulder closures for sign work, Monday to Friday from 8 a.m. to 5 p.m. through November 20.
*NEW* Mile marker 302 to 305, northbound – Overnight right lane closure for pavement patching, 8 p.m. Monday to 7 a.m. Tuesday.
Mile marker 315 to 316, northbound and southbound – Overnight alternating lane closures for inspection of Route 7 overpass bridge at exit 315 interchange, 8 p.m. Friday to 7 a.m. Saturday.
PRIMARY ROADS
*UPDATE* Route 11 (Valley Pike) – Northbound lane shifts between Route 652 (Apple Valley Road) and Route 651 (Shawnee Drive) for turn-lane construction, Monday to Friday from 9 a.m. to 3 a.m. through November 13.
Route 37 – Northbound and southbound alternating lane closures between Route 11 (Valley Pike) and Route 11 (Martinsburg Pike) for shoulder widening and rumble strip installation. Monday to Thursday from 9 a.m. to 3:30 p.m. Monday through Thursday nights from 7 p.m. to 5 a.m. Friday and Saturday nights from 10 p.m. to 10 a.m. Estimated completion November 10.
*UPDATE* Route 50 (Northwestern Turnpike) – Flagger traffic control for utility work between Route 817 (Magic Mountain Road) and Route 614 (Back Mountain Road), Tuesday from 8 a.m. to 3 p.m.
Route 55/48 (Wardensville Pike) – Alternating lane closures for utility work between Shenandoah County line and West Virginia line, 9 a.m. to 3:30 p.m. through January 10.
Route 277 (Fairfax Pike) – Overnight alternating lane closures as needed for roadway and utility work between Route 647 (Aylor Road) and Route 641 (Double Church Road), Sunday through Thursday nights from 8 p.m. to 6 a.m. Shoulder closures 24/7. Work is part of roadway reconstruction project with completion in late 2022.
SECONDARY ROADS
Route 623 (Fromans Road) – Closed for bridge replacement at Cedar Creek just west of Route 622 (Cedar Creek Grade) at Shenandoah County line. Follow posted detour. Estimated project completion June 2021.
*NEW* Route 627 (Reliance Road) – Shoulder closures for sign work between Route 11 (Valley Pike) and I-81 exit 302 interchange, Monday to Friday from 8 a.m. to 5 p.m. through November 20.
Route 641 (Double Church Road) – Flagger traffic control between Route 1450 (Driftwood Drive) and Route 1049 (Buckingham Drive) for roadway and utility work related to roadway reconstruction, Monday to Friday from 9 a.m. to 2:30 p.m. through November 30.
*NEW* Route 652 (Shawnee Drive) – Eastbound right lane closure for turn-lane construction between Route 816 (Battaile Drive) and Winchester city limits, Monday to Friday from 7 a.m. to 4:30 p.m.
*NEW* Route 707 (Hollow Road) – Road closed between Route 733 (Fletcher Road) and Route 610 (Parishville Road), Tuesday and Wednesday from 8 a.m. to 4 p.m.
Route 1085 (Stickley Drive) – Closed just south of Route 277 (Fairfax Pike) for utility work and roadway reconstruction. Detour using Route 1012 (Town Run Lane). Estimated completion December 18.
Various roads – Flagger traffic control for utility tree trimming, Monday to Friday during daylight hours.
CLARKE COUNTY
PRIMARY ROADS
No lane closures reported.
SECONDARY ROADS
No lane closures reported.
WARREN COUNTY
INTERSTATE 66
Mile marker 0 to 14, eastbound and westbound – Alternating lane closures for bridge maintenance at various locations, Monday through Thursday from 7 a.m. to 3 p.m. through November 13.
*NEW* Mile marker 1 to 3, eastbound and westbound – Alternating lane closures for inspection of Route 842 overpass bridge, Monday from 8 a.m. to 6 p.m.
INTERSTATE 81
No lane closures reported.
PRIMARY ROADS
No lane closures reported.
SECONDARY ROADS
Various roads – Flagger traffic control for utility tree trimming, Monday to Friday during daylight hours.
Vegetation management may take place district wide on various routes. Motorists are reminded to use extreme caution when traveling through work zones.
Traffic alerts and traveler information can be obtained by dialing 511. Traffic alerts and traveler information also are available at http://www.511Virginia.org.
The VDOT Customer Service Center can assist with reporting road hazards, asking transportation questions, or getting information related to Virginia’s roads. Call 800-FOR- ROAD (800-367-7623) or use its mobile friendly website at https://my.vdot.virginia.gov/. Agents are available 24 hours-a-day, seven days a week.
The Staunton District Twitter feed is at @VaDOTStaunton. VDOT can be followed on Facebook, Flickr, Twitter and YouTube. RSS feeds are also available for statewide information. The VDOT Web page is located at http://www.VirginiaDOT.org.
(END)
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.