VDOT News - Northern Virginia

RELEASE:

CONTACT:
IMMEDIATE

Michelle Holland 703-586-0487
Michelle.Holland@vdot.virginia.gov

NOVA-189626

Dec. 30, 2021



Overnight Ramp Closures at Multiple I-66 Interchanges, January 4-7, for the Transform 66 Outside the Beltway Project

FAIRFAX – Temporary ramp closures are scheduled to occur during the overnight hours next week at the following I-66 interchanges as part of the Transform 66 Outside the Beltway Project.

Details include:

Tuesday, January 4, through Friday, January 7
Ramp from I-495 North to I-66 West
The ramp will be closed nightly from 9:30 p.m. to 4:30 a.m. for a concrete pour and overhead bridge work. Traffic will be directed to continue north to Route 7 (Leesburg Pike) West, stay to the right to I-495 South, then follow signs to I-66 West. 

Ramp from I-495 North to I-66 East
The ramp will be closed nightly from 9:30 p.m. to 4:30 a.m. for a concrete pour and overhead bridge work. Traffic will be directed to continue north to Route 7 East, travel about one mile, then follow signs to I-66 East.

Wednesday night, January 5, and Thursday night, January 6
Ramp from Route 29 (Lee Highway) South Gainesville to I-66 East
The ramp will be closed from midnight to 4 a.m. each night for utility work. Traffic will be directed to continue south to the traffic signal at Virginia Oaks Drive, stay to the left and make a U-turn from the left most left-turn lane onto Route 29 North, then follow signs to I-66 East.

Construction and lane closure updates are available at Transform66.org and on Twitter @VaDOTNOVA. To receive updates automatically by email, sign up here.  

 

###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Aug. 29, 2023