Overnight Bridge Demolition Continues at I-66/Route 50 Interchange Next Week (September 7-11) with Overnight Closure of Ramp from Route 50 East to I-66 East

FAIRFAX – Continued demolition of the old Route 50 bridges over I-66 will require the ramp from Route 50 East to I-66 East to be closed during overnight hours Tuesday, September 7, through Saturday, September 11. Drivers traveling in the area should expect delays and consider using alternate routes. Details include:

Tuesday night, September 7, through Saturday night, September 11

  • The ramp from eastbound Route 50 to eastbound I-66 will be closed from midnight to 4 a.m. Tuesday through Thursday nights, and midnight to 5 a.m. Friday and Saturday nights.
  • Traffic will be directed farther east, stay to the left and use the left-most left turn lane to make a U-turn at the traffic signal at Waples Mill Road, then stay to the right and follow signs to I-66 East.

All work is weather dependent and will be rescheduled if inclement conditions occur.

Route 50 Bridge Demolition Activities Next Week:

  • Crews will begin demolition of the old westbound Route 50 Bridge over the ramp from eastbound Route 50 to eastbound I-66, with removal of the concrete bridge deck using jackhammers, saw cutters, and hoe rams, followed by removal of steel bridge beams.
  • Demolition work will occur during overnight hours when over travel lanes of I-66. 
  • For updates on demolition progress visit transform66.org/route50

Route 50 Bridge Demolition Progress to Date:

  • Demolition of the old westbound Route 50 Bridge over I-66 was completed on July 16.
  • Demolition of the old eastbound Route 50 Bridge over I-66 was completed on August 13.

Ramp Closure and Detour: Tuesday night, September 7, through Saturday night, September 11

The I-66/Route 50 Interchange is being rebuilt and improved as part of the Transform 66 project. The new interchange will have express lanes access to and from the east, and a new shared-use path.  

Construction and lane closure updates are available at Transform66.org and on Twitter @VaDOTNOVA. To receive updates automatically by email, sign up here.

 

###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Jan. 19, 2023