Nine-Day Closure of North Glebe Road in Arlington Begins Aug. 13
Detour in place during Pimmit Run bridge deck and beam replacement
Update 8/23/21: Due to last week's inclement weather, the new reopening date for Glebe Road is Monday, Aug. 30 at 5 a.m.
ARLINGTON – North Glebe Road (Route 120) between Military Road and Route 123 (Chain Bridge Road) will be closed to traffic for about nine days beginning Friday night, Aug. 13 to efficiently replace the entire bridge deck and beams over Pimmit Run, just west of Route 123, according to the Virginia Department of Transportation.
North Glebe Road will close at 10 p.m. Aug. 13 and is scheduled to reopen to traffic by 5 a.m. Monday, Aug. 23.
Vehicle traffic will be detoured via Route 123, Kirby Road (Route 695) and Chesterbrook Road (Route 689) back to North Glebe Road.
To help pedestrians get around the closure, a free shuttle for up to 12 passengers will be available Saturday, Aug. 14 through Sunday, Aug. 22 from 7 a.m. to 7 p.m. each day. Signs and posters with a phone number (240-300-3264) and shuttle information will be posted at both ends of the bridge over Pimmit Run, with the shuttle provided within ten minutes of a call (if needed, a free accessible shuttle will be provided within 30 minutes of a call). Each shuttle ride will last approximately five minutes.
The portion of the Potomac Heritage Trail under the Pimmit Run bridge will remain open, with trail access controlled by flaggers when needed.
Construction began in April on the overall project to rehabilitate North Glebe Road over Pimmit Run, which was originally built in 1973 and currently carries about 13,000 vehicles a day. The work includes improvements that will extend the overall life of the bridge and improve safety for drivers, bicyclists and pedestrians. They include:
- Replacing bridge beams, deck and barriers
- Repairing, waterproofing and providing corrosion protection to abutments and piers
- Replacing barriers and railings along bicycle and pedestrian connection to trails
- Upgrading guardrails and drainage
The $9.9 million project is financed with federal and state funds, including State of Good Repair funding used for bridges. The project is scheduled for completion this fall.
Learn more about the project at www.virginiadot.org/glebeoverpimmit.