Overnight Closures and Traffic Stoppages on I-66 East and West near Jermantown Road in Fairfax Continue Next Week for Overhead Bridge Work

FAIRFAX – Bridge beam installation for the new Jermantown Road Bridge over I-66 will continue next week with lane closures and stoppages during overnight hours on I-66 as part of the Transform 66 Outside the Beltway Project. Work is scheduled to occur in both directions on Monday night, November 9; the remaining nights (Tuesday, November 10, through Friday, November 13) are planned to impact only I-66 West. Drivers should expect delays if traveling in this area during these times and should consider using alternate routes.

Details include:

Monday, November 9
I-66 East and West between Route 50 and Route 123 (Chain Bridge Road)

  • I-66 East will be reduced to one travel lane approaching Jermantown Road from 9 p.m. to 4:30 a.m.
  • I-66 West will be reduced to two travel lanes approaching Jermantown Road from 9 p.m. to 5 a.m.
  • Drivers should expect periodic brief stoppages of up to 10 minutes on eastbound and westbound I-66 between 10:30 p.m. and 4 a.m.
  • All lanes will reopen on I-66 East by 4:30 a.m. and on I-66 West by 5 a.m.

Tuesday, November 10, and Thursday, November 12
I-66 West from Route 123 to Jermantown Road

  • Two right lanes will be closed each night between Route 123 and Jermantown Road from 9 p.m. to 4:30 a.m.
  • All lanes will reopen by 4:30 a.m.

Wednesday, November 11, and Friday, November 13
I-66 West from Route 123 to Jermantown Road

  • I-66 West will be reduced to one travel lane each night approaching Jermantown Road from 9 p.m. to 4:30 a.m.
  • Drivers should expect periodic brief stoppages of up to 10 minutes on westbound I-66 between 10:30 p.m. and 4 a.m. each night for crews to set bridge beams into place.
  • All lanes will reopen by 4:30 a.m. Thursday, November 12, and by 6 a.m. Saturday, November 14.

All work is weather dependent and will be rescheduled if inclement conditions occur. 

Message boards on I-66 East and West are providing advance notice of lane closures and traffic stoppages. 

The Jermantown Road Bridge over I-66 is being reconstructed as part of the Transform 66 Outside the Beltway Project.

Construction and lane closure updates are available at Transform66.org and on Twitter @VaDOTNOVA. To receive project updates automatically by email, sign up here.   

 

###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Aug. 17, 2023