BEAM INSTALLATION SCHEDULED FOR FUTURE I-95 SOUTHBOUND BRIDGE OVER ROUTE 17 IN STAFFORD
All Route 17 traffic near I-95 will be stopped intermittently between 11 p.m. and 3 a.m. for several weeks starting Tuesday, March 30 through early Friday, April 2
FREDERICKSBURG, Va. – Crews will start installing the new steel beams on the future Interstate 95 southbound bridge over Route 17 in Stafford County as part of the I-95 Southbound Rappahannock River Crossing project.
The beam installation will require intermittent full traffic stops on Route 17 over the next several weeks.
Starting at 8 p.m. tomorrow night, March 30, the right lane on Route 17 southbound between Sanford Drive and Short Street will close to get equipment into place ahead of the beam lifts.
All Route 17 southbound traffic will be stopped up to 30 minutes at a time between 11 p.m. and 3 a.m. each evening this week to lift and secure the bridge beams into place.
Weather permitting, lane closures on Route 17 southbound are scheduled at the following times:
Tuesday, March 29 – Friday, April 2
• 8 p.m. – 10:59 p.m. – Single lane closure
• 11 p.m. to 3 a.m. – Full traffic stop up to 30 minutes
• 3 a.m. – 6:59 a.m. – Single lane closure
• 7 a.m. – All lanes open.
Virginia State Police will assist with traffic control in the work zone.
Project Background
Several megaprojects are under construction to reduce congestion and improve reliability on I-95 in the Fredericksburg area.
Construction on the I-95 Southbound Rappahannock River Crossing began in August 2018 and will be underway through May 2022.
The $132 million project is building three additional travel lanes between Exit 133 in Stafford and Exit 130 (Route 3) in Fredericksburg, and will build a new bridge span over the Rappahannock River.
New lanes are being built parallel to the existing southbound lanes in the median. With nearly 150,000 vehicles a day traveling on I-95 near the Rappahannock River, the new lanes will allow local traffic to travel along I-95 between interchanges separated from regional and interstate traffic traveling through the Fredericksburg area.
The I-95 Northbound Rappahannock River Crossing project will build additional northbound travel lanes between the same interchanges. Preliminary construction activities began in summer 2020, and new lanes will open to traffic in early 2024.
Both Rappahannock River Crossing projects will connect with 95 Express Lanes, which are being extended over 10 additional miles in Stafford to the Route 17 area.
The 95 Express Lanes Fredericksburg Extension is under construction and contractually will open to traffic in late 2022.
For additional information, please visit the Improve 95 website.
511Virginia
Motorists can find real-time information on lane closures, work zones, traffic and other incidents on 511Virginia.
Download the free mobile 511Virginia app for Apple and Android devices to stay connected, or visit www.511Virginia.org. Motorists also can reach 511Virginia by calling 511 from any phone in Virginia.
(END)
VDOT’s 14-county Fredericksburg District includes the counties of Caroline, King George, Spotsylvania and Stafford in the Fredericksburg area; Northumberland, Richmond, Lancaster and Westmoreland counties in the Northern Neck; Essex, Gloucester, King & Queen, King William, Mathews and Middlesex counties in the Middle Peninsula.
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.