VDOT News - Fredericksburg
RELEASE: CONTACT: |
IMMEDIATE Darragh Frye 540-899-4119 Darragh.Frye@VDOT.Virginia.Gov |
FRED-153808 Dec. 19, 2019 |
ALL FOUR LANES OPEN ON COURTHOUSE ROAD IN STAFFORD
Road widened from two to four lanes from west of Austin Ridge Drive to Winding Creek Road and Ramoth Church Road intersection
FREDERICKSBURG, Va . – All four travel lanes on Route 630 (Courthouse Road) in Stafford County are now open to traffic from west of Austin Ridge Drive to the Winding Creek Road and Ramoth Church Road intersection.
Traffic began traveling on all four eastbound and westbound lanes earlier today after crews removed construction barrels and signs.
Earlier this month, a new diverging diamond interchange opened at Exit 140 at Interstate 95 in Stafford. At the same time, a new four-lane Hospital Center Boulevard extension opened west of Route 1. But Courthouse Road remained two lanes west of Austin Ridge Drive until today, when the four-lane portion opened to traffic.
Today’s opening is another major milestone in the $195 million project to expand capacity and improve travel in the Courthouse Road area.
Construction is still underway to finish building the new I-95 southbound off-ramp at Exit 140. Ramp traffic will continue to be detoured as crews work to raise the elevation of the new off-ramp to match the height of the diverging diamond interchange and I-95 overpass bridges. Crews anticipate opening the new ramp and lifting the detour next week.
Click here to view a map of the I-95 southbound exit ramp detour.
Motorists traveling from I-95 southbound to Courthouse Road should follow the posted detour signs.
Project Background
Construction on the Exit 140 interchange and Courthouse Road widening project began in July 2017. All work will be finished by July 31, 2020.
Construction crews will focus on finishing the following project elements in 2020:
- Expanded Park & Ride commuter parking at Exit 140: New Park & Ride lots are under construction north and south of the future Old Courthouse Road. Together, the lots will offer around 1,100 parking spaces. The southern lot will have a dedicated pickup and dropoff area for buses, carpools, and vanpools.
- New sidewalk and shared use path: Crews will continue building new sidewalk from the Park & Ride lots east along Old Courthouse Road to the Stafford County Government Center, and a shared use path from Austin Ridge Drive to the Park & Ride lots through the interchange. A new, shared use path from Winding Creek Elementary School near the Ramoth Church Road/Winding Creek Road intersection to west of Austin Ridge Drive is now open.
Courthouse Road carries an average of 16,000 vehicles a day and around 136,000 vehicles a day travel on I-95 near Exit 140.
To learn more on this project, please visit the project page at www.VirginiaDOT.org/Exit140 and VDOT’s innovative intersections and interchanges page on diverging diamond interchanges (DDI).
(END)
VDOT’s 14-county Fredericksburg District includes the counties of Caroline, King George, Spotsylvania and Stafford in the Fredericksburg area; Northumberland, Richmond, Lancaster and Westmoreland counties in the Northern Neck; Essex, Gloucester, King & Queen, King William, Mathews and Middlesex counties in the Middle Peninsula.
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.