VDOT News - Culpeper

RELEASE:

CONTACT:
IMMEDIATE

Lou Hatter 540-717-2890
Lou.Hatter@vdot.virginia.gov

Will Merritt 540-829-7370
William.Merritt@vdot.virginia.gov


CULP 2021-041

Sept. 2, 2021



RT. 647 BRIDGE PROJECT REOPENS AHEAD OF SCHEDULE
South Anna River bridge opens to traffic about three weeks early

CULPEPER — The Route 647 (Harts Mill Road) bridge over the South Anna River in Louisa County reopened to traffic Thursday afternoon — about three weeks ahead of schedule.   

VDOT contractor Fairfield-Echols, LLC of Fishersville replaced the 89-year-old truss bridge. The new bridge is open to all legal-weight vehicles.

The bridge was closed on Jan. 29 and was scheduled to reopen on Sept. 22.

For more information about Virginia’s bridges and VDOT’s bridge inspection program, including current conditions of the state’s bridges, FAQs and video of a bridge inspection, visit VDOT’s website, http://www.virginiadot.org/info/Bridge.asp.

 (END)



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.