VDOT News - Culpeper
RELEASE: CONTACT: |
IMMEDIATE Lou Hatter (540) 717-2890 Lou.Hatter@VDOT.Virginia.gov |
CULP 2021-0048 Oct. 20, 2021 |
CONSTRUCTION BEGINS ON U.S. 250/RT. 151 ROUNDABOUT
Speed limit lowered to 25 mph through work zone at Afton, watch for workers and equipment
CULPEPER — Construction activity will begin next week on a roundabout at the intersection of Route 250 (Rockfish Gap Turnpike) and Route 151 (Critzer Shop Road). The project will improve safety and traffic flow at the busy intersection while managing vehicle speeds and correcting geometric deficiencies that have been identified as contributing factors in crashes at the intersection.
Traffic flow through the current “T” intersection is controlled by a traffic signal that was installed in 2017 as a temporary measure along with flashers to warn traffic to slow in advance of the intersection. The roundabout will improve safety since all traffic must slow to enter the roundabout. In a roundabout traffic on the approaches must yield to vehicles in the roundabout.
During construction traffic will be maintained through the project although drivers may encounter some lane closures with traffic controlled by flaggers. Work will be limited to Monday through Friday, so weekend traffic will not be affected by construction activities.
Information about the project is available on the Virginia Department of Transportation’s web site at: Albemarle Co. Design-Build Projects. That page also has a link to a graphic of the construction phases and lane alignments during each phase.
The speed limit on both U.S. 250 and Route 151 has been lowered to 25 miles per hour on the intersection approaches and through the work zone. Motorists should drive with extreme caution as they approach the construction project since workers may be near the travel lanes and slow-moving equipment and vehicles may enter or exit the travel lanes in the work zone.
The U.S. 250 / Route 151 roundabout project is one of six improvement projects in a $28.5 million design-build bundled contract with Curtis Contracting Inc., of West Point, Va. The U.S. 250 / Route 151 roundabout project will cost $4.8 million. The other projects include the interchange improvements at U.S. 29 and Interstate 64, Exit 118, improvements to the Fontaine Avenue exit from U.S. 29 north, and the Rio Mills connector road, all of which are substantially complete.
The diverging diamond interchange on U.S. 250 at I-64 Exit 124 is under construction, as is a roundabout at Route 20 (Stony Point Road) and Route 649 (Proffit Road) in northern Albemarle County. The contract completion date for all six projects is February 2023.
Current traffic conditions and other real-time travel information can be found on the 511 Virginia website, the free VDOT 511 mobile app or by calling 511 from any phone in Virginia. VDOT updates are also on Facebook and the district’s Twitter account, @VaDOTCulp.
(END)
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.